Test Package

  • You can display “Test Package” main window via “Work Flow” link within the upper bar in Home Page or via “Test Package” Link within Quick Links.
  • Log in to the system, Click on the “Test Package” Link4  from the Quick Links Menu.
  • Or, From the Upper bar in Home Page, Click on “Workflow” Link5  which will open a form containing a summarized Workflow of the system. Then, Click “Test Package” icon.5
  • A “Test Package” window will be opened, with all the Test Packages within the system displayed with an “Add” button.
  • Within the grid view containing all the Test Packages within the system icons: Select 2, Edit 3, Delete4 , “View Details” 2,“Docs”7 , “Assign”6 ,”Issue” 7, “Accept”8 and “Reject” 10.8
  • Icon “Accept”8  within the grid view is only enabled when all the Test Package’s joints are closed and ready for HT.
  • Clicking “”Accept”8  icon, to accept selected joint.
  • Icon “Reject”10 within the grid view is only enabled when all the Test Package’s joints are closed and ready for HT.
  • Clicking “Reject” icon 10, to reject selected joint.
  • Clicking “View Details”2 icon, a window is opened where selected Test Package’s detailed Report is displayed. Clicking “Assign” icon 6, window is opened where you can select joints to enter the selected test package
  • Clicking “Issue”7 icon, a window is opened where selected Test Package’s detailed Report is displayed along with all selected Test Package history detailed. Also displayed all Test Package’s Line/Tanks details.
  • Clicking “Select” 2 icon, “Assigned joints” panel is displayed with a grid view containing all joints assigned to select Test Package.
Tagged with: ,
Posted in Test Package, Welding Manager Training